top of page

Northshore Reconstruct - Project Update 5/7

brothschadl
May 7
2 min read

Good Afternoon,


Construction has been in full swing this week, and significant progress has been made. Looking ahead for the next week, there will be some changes to construction access and work limits. Please read on below for additional details:


Past Week Construction Activities

The Utility Contractor has:

  • Completed installation of the 60-inch storm sewer

  • Finished construction of the riprap at the lakeside flared ends

  • Completed the 36-inch and 48-inch inlets on the north side of Northshore Drive

The Grading Contractor has:

  • Begun removal of the old subbase on Northshore Drive

  • Completed construction of the temporary access road on the north side of Northshore Drive


Weekly Progress Photos


Upcoming Work Limit & Traffic Impacts

Later in next week, the road closure will be extended from its current location east of Penrose to the east side of the Elementary School driveways. Residents within this area will still need to follow the designated detour; however, access will be maintained through the temporary road on the north side of Northshore Drive.


Please be aware that there may be periods when vehicle access to individual driveways is temporarily unavailable. Our project team will actively monitor these situations and will make every effort to coordinate directly with affected homeowners.


Upcoming Construction Activities

The Utility Contractor will:

  • Continue storm sewer installation along Northshore Drive between Leisure Lane and Penrose Drive

  • Begin installation of temporary water lines ahead of water installations

  • Prepare for installation of erosion control concrete block mats at 72-in and 60-in outfalls into McCook Lake


The Grading Contractor will:

  • Begun removal of Northshore asphalt west of Penrose

  • Continue earthwork operations along Northshore Drive corridor


If you have any questions or concerns, please do not hesitate to contact our project team. Thank you for your patience and cooperation as we continue progressing on this project.


NORTH SIOUX CITY STRONG

Northshore & Penrose Recovery Information Site

logo - white.png

(605) 232-4276

504 River Drive

North Sioux City, SD 57049

www.northsiouxcity-sd.gov

Stockwell Logo White.png

(605) 338-6668

801 N Phillips Ave, Ste. 100

Sioux Falls, SD 57104

www.stockwellengineers.com

bottom of page