top of page

Northshore Reconstruct - Project Update 5/16

brothschadl
May 16
1 min read

Good Morning,


Construction has been in full swing this week, and good progress has been made. Looking ahead for the next week, there will be some additional major milestones completed as well.


Past Week Construction Activities

The Utility Contractor has:

  • Started subgrade preparation for the erosion control block mat

  • Completed approximately 75% of the 48-inch storm sewer from 45 Northshore to Penrose


The Grading Contractor has:

  • Completed removal of old subbase on Northshore Drive

  • Begun Northshore Drive corridor grading.


Weekly Progress Photos


Upcoming Construction Activities

The Utility Contractor will:

  • Continue storm sewer installation along Northshore Drive between Leisure Lane and Penrose Drive

  • Begin installation of temporary water lines ahead of water installations

  • Install erosion control concrete block mats at 72-in and 60-in outfalls into McCook Lake


The Grading Contractor will:

  • Continue earthwork operations along Northshore Drive corridor


If you have any questions or concerns, please do not hesitate to contact our project team. Thank you for your patience and cooperation as we continue progressing on this project.


NORTH SIOUX CITY STRONG

Northshore & Penrose Recovery Information Site

logo - white.png

(605) 232-4276

504 River Drive

North Sioux City, SD 57049

www.northsiouxcity-sd.gov

Stockwell Logo White.png

(605) 338-6668

801 N Phillips Ave, Ste. 100

Sioux Falls, SD 57104

www.stockwellengineers.com

bottom of page