Northshore Reconstruct - Project Update 5/16
Good Morning,
Construction has been in full swing this week, and good progress has been made. Looking ahead for the next week, there will be some additional major milestones completed as well.
Past Week Construction Activities
The Utility Contractor has:
Started subgrade preparation for the erosion control block mat
Completed approximately 75% of the 48-inch storm sewer from 45 Northshore to Penrose
The Grading Contractor has:
Completed removal of old subbase on Northshore Drive
Begun Northshore Drive corridor grading.
Weekly Progress Photos
Upcoming Construction Activities
The Utility Contractor will:
Continue storm sewer installation along Northshore Drive between Leisure Lane and Penrose Drive
Begin installation of temporary water lines ahead of water installations
Install erosion control concrete block mats at 72-in and 60-in outfalls into McCook Lake
The Grading Contractor will:
Continue earthwork operations along Northshore Drive corridor
If you have any questions or concerns, please do not hesitate to contact our project team. Thank you for your patience and cooperation as we continue progressing on this project.